HICL DREDGER TESTING SYSTEM

HICL Dredger Testing System

 

Dredger in Testing Center

Dredger Testing & Launching Center are Available in our Shipyard


 

In order to guarantee good performance and safety of our cutter suction dredger, all our products will be tested in the testing center before ex-factory, it is tested like the machine working in the customer’s working site. Performance and safety will be tested and recorded in the testing process. Usually, the buyer can also supervised the testing process before dismantle the dredge.

 

 A. Preparing work before Dredger Testing

1)  Customers will be invited to watch dredger test, radio and pictures will email to buyers.

2)  Every parts and connections of dredger should be checked strictly before test. 

3)  Oil and cooling water should be ready for dredger test.

 

B. Dredger Testing Contents

1) Work condition of electricity connection of dredger should be checked .
2) Emergency pump to check operation conditions of hydraulic controlling system,
3)  The speed and power of diesel engine should be tested. 

4)  Dredging pump will be tested and rotates at different speed with fresh water.

5)  In order to check the operation of various hydraulic machinery and values, the main hydraulic pump will be opened and hydraulic system load performance should be tested. 

 

C. After Testing 

 
1)  All equipment performances and testing recorded will be printed as report for customers' reference.

2)  after testing, all work about dredger dismantle should be prepared and let customer knows when and what time will do the delivery.